Cost Management Interview Questions And Answers
Download Cost Management Interview Questions and Answers PDF
Elevate your Cost Management interview readiness with our detailed compilation of 49 questions. Our questions cover a wide range of topics in Cost Management to ensure you're well-prepared. Whether you're new to the field or have years of experience, these questions are designed to help you succeed. Download the free PDF to have all 49 questions at your fingertips. This resource is designed to boost your confidence and ensure you're interview-ready.
49 Cost Management Questions and Answers:
Cost Management Job Interview Questions Table of Contents:
1 :: Analogous estimating:
A. Uses bottom-up estimating techniques
B. Is used most frequently during the executing processes of the project
C. Uses top-down estimating techniques
D. Uses actual detailed historical cost
C. Uses top-down estimating techniques
Read More2 :: All of the following are outputs of the Estimate Costs process EXCEPT:
A. An understanding of the cost risk in the work that has been estimated
B. The prevention of inappropriate changes from being induded in the cost baseline
C. An indication of the range of possible costs for the project
D. Documentation of any assumptions made during the Estimate Costs process
B. The prevention of inappropriate changes from being induded in the cost baseline
Read More3 :: If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV)?
A. 350
B. -75
C. 400
D. -50
D. -50
Read More4 :: One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
Divide by CPI
Read More5 :: Estimate at completion (EAC) is a periodic evaluation of:
A. The cost of work completed
B. The value of work performed
C. The anticipated total cost at project completion
D. What it will cost to finish the job
C. The anticipated total cost at project completion
Read More6 :: The main focus of life cycle costing is to:
A. Estimate installation costs
B. Estimate the cost of operations and maintenance
C. Consider installation costs when planning the project costs
D. Consider operations and maintenance costs in making project decisions
D. Consider operations and maintenance costs in making project decisions
Read More7 :: Cost performance measurement is BEST done through which of the following?
A. Asking for a percent complete from each team member and reporting that in the monthly progress report
B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance
C. Using the 50/50 rule and making sure the life cyde cost is less than the project cost
D. Focusing on the amount expended last month and what will be expended the following month
B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance
Read More8 :: A cost performance index (CPI) of 0.89 means:
A. At this time, we expect the total project to cost 89 percent more than planned
B. When the project is completed we will have spent 89 percent more than planned
C. The project is only progressing at 89 percent of the rate planned
D. The project is only getting 89 cents out of every dollar invested
D. The project is only getting 89 cents out of every dollar invested
Read More9 :: A schedule performance index (SPI) of 0.76 means:
A. You are over budget
B. You are ahead of schedule
C. You are only progressing at 76 percent of the rate originally planned
D. You are only progressing at 24 percent of the rate originally planned
C. You are only progressing at 76 percent of the rate originally planned
Read More10 :: Which of the following is NOT needed in order to come up with a project estimate?
A. A WBS
B. A network diagram
C. Risks
D. A change control system
D. A change control system
Read More11 :: Which of the following is an example of a parametric estimate?
A. Dollars per module
B. Learning bend
C. Bottom-up
D. CPM
A. Dollars per module
Read More12 :: A rough order of magnitude estimate is made during which project management process group?
A. Planning
B. Closing
C. Executing
D. Initiating
D. Initiating
Read More13 :: A cost baseline is an output of which cost management process?
A. Estimate Activity Resources
B. Estimate Costs
C. Determine Budget
D. Control Costs
C. Determine Budget
Read More14 :: During which project management process group are budget forecasts created?
A. Monitoring and controlling
B. Planning
C. Initiating
D. Executing
A. Monitoring and controlling
Read More15 :: Project setup costs are an example of:
A. Variable costs
B. Fixed costs
C. Overhead costs
D. Opportunity costs
B. Fixed costs
Read More16 :: Value analysis is performed to get:
A. More value from the cost analysis
B. Management to buy into the project
C. The team to buy into the project
D. A less costly way of doing the same work
D. A less costly way of doing the same work
Read More18 :: Which of the following represents the estimated value of the work actually accomplished?
A. Earned value (EV)
B. Planned value (PV)
C. Actual cost (AC)
D. Cost variance (CV)
A. Earned value (EV)
Read More19 :: Which of the following are ALL items included in the cost management plan?
A. The level of accuracy needed for estimates, rules for measuring cost performance, specifications for how duration estimates should be stated
B. Specifications for how estimates should be stated, rules for measuring cost performance, the level of accuracy needed for estimates
C. Rules for measuring team performance, the level of accuracy needed for estimates, specifications for how estimates should be stated
D. Specifications for how estimates should be stated, the level of risk needed for estimates, rules for measuring cost performance
B. Specifications for how estimates should be stated, rules for measuring cost performance, the level of accuracy needed for estimates
Read More20 :: Your project has a medium amount of risk and is not very well defined. The sponsor hands you a project charter and asks you to confirm that the project can be completed within the project cost budget. What is the BEST method to handle this?
A. Build the estimate in the form of a range of possible results
B. Ask the team members to help estimate the cost based on the project charter
C. Based on the information you have, calculate a parametric estimate
D. Provide an analogous estimate based on past history.
A. Build the estimate in the form of a range of possible results
Read More21 :: The cost contingency reserve should be:
A. Hidden to prevent management from disallowing the reserve
B. Added to each activity to provide the customer with a shorter critical path
C. Maintained by management to cover cost overruns
D. Added to the base costs of the project to account for risks
D. Added to the base costs of the project to account for risks
Read More22 :: The seller tells you that your activities have resulted in an increase in their costs. You should:
A. Recommend a change to the project costs
B. Have a meeting with management to find out what to do
C. Ask the seller for supporting information
D. Deny any wrongdoing
C. Ask the seller for supporting information
Read More23 :: Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
A. Eliminate risks in estimates and reestimate
B. Meet with the sponsor to find out what work can be done sooner
C. Cut quality
D. Decrease scope
A. Eliminate risks in estimates and reestimate
Read More24 :: A new store development project requires the purchase of various equipment, machinery, and furniture. The department responsible for the development recently centralized its external purchasing process and standardized its new order system. In which document can these new procedures be found?
A. Project scope statement
B. WBS
C. Staffing management plan
D. Organizational policies
D. Organizational policies
Read More25 :: Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:
A. Agree to analogous estimating, as it is a form of expert judgment
B. Suggest life cyde costing as a compromise
C. Determine why the sponsor wants such an accurate estimate
D. Try to convince the sponsor to allow expert judgment because it is typically more accurate
A. Agree to analogous estimating, as it is a form of expert judgment
Read More