Manager Construction Frequently Asked Questions in various Construction Manager job Interviews by interviewer. The set of questions here ensures that you offer a perfect answer posed to you. So get preparation for your new job hunting
45 Construction Manager Questions and Answers:
Table of Contents:
![Behavioral Construction Manager Job Interview Questions and Answers](https://globalguideline.com/public/images/interview/30.png)
2 :: Performance of specific task in CPM, is known:
A. Dummy
B. Event
C. Activity
D. Contract
C. Activity
3 :: The Construction team means:
A. an engineer
B. an architect
C. an owner
D. a contractor
E. all the above
E. all the above
5 :: Technique for the establishing and maintaining priorities among the various jobs of a project, is known:
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
B. Critical ratio scheduling
6 :: Pick up incorrect statement from following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to scale from left to right
E. Each activity consumes a given time
D. The arrows are drawn to scale from left to right
9 :: Cost of project is more than:
A. one lac
B. two lacs
C. three lacs
D. four lacs
E. five lacs.
A. one lac
10 :: The Completion of activity on the CPM network diagram, is generally known:
A. Event
B. Node
C. Connector
D. All the above
D. All the above
12 :: KThe Final technical authority of project lies with:
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
D. Chief Engineer
14 :: The Various activities of project, are shown on bar charts by:
A. vertical lines
B. horizontal lines
C. dots
D. crosses
B. horizontal lines
15 :: The Military Organization is known as:
A. line organisation
B. line and staff organisation
C. functional organisation
D. none of these
A. line organisation
16 :: Pick up incorrect statement from following:
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
E. None of these
C. The activity which consumes maximum time, is called a node
18 :: The dummy activity:
A. is artificially introduced
B. is represented by a dotted line
C. does not consume time
D. all the above.
D. all the above.
25 :: Difference between time avail-to do a job and time required to do the job, is known as:
A. event
B. float
C. duration
D. constraint
B. float