The technical planning Object is:

A. preparation of specifications
B. preparation of estimates
C. initiating the procurement action of resources
D. taking remedial action for likely bottleneck in the execution
E. all the above

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

E. all the above