First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)

Construction Manager Interview Question
Construction Manager Interview Question

Answer:

A. Bar chart method

Download Construction Manager Interview Questions And Answers PDF

Previous QuestionNext Question
During night work who does CM contact?If TL is the latest allowable event occurrence time, total activity slack(s), is equal to:

A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above