Which of the following is NOT needed in order to come up with a project estimate?

A. A WBS
B. A network diagram
C. Risks
D. A change control system

Cost Management Interview Question
Cost Management Interview Question

Answer:

D. A change control system

Download Cost Management Interview Questions And Answers PDF

Previous QuestionNext Question
A schedule performance index (SPI) of 0.76 means:

A. You are over budget
B. You are ahead of schedule
C. You are only progressing at 76 percent of the rate originally planned
D. You are only progressing at 24 percent of the rate originally planned
Which of the following is an example of a parametric estimate?

A. Dollars per module
B. Learning bend
C. Bottom-up
D. CPM