Cost Management Question:
Download Questions PDF

A cost baseline is an output of which cost management process?

A. Estimate Activity Resources
B. Estimate Costs
C. Determine Budget
D. Control Costs

Cost Management Interview Question
Cost Management Interview Question

Answer:

C. Determine Budget

Download Cost Management Interview Questions And Answers PDF

Previous QuestionNext Question
A rough order of magnitude estimate is made during which project management process group?

A. Planning
B. Closing
C. Executing
D. Initiating
During which project management process group are budget forecasts created?

A. Monitoring and controlling
B. Planning
C. Initiating
D. Executing