Top Payables Management Interview Preparation Guide Download PDF
Payables Management related Frequently Asked Questions in various Payables Management based job Interviews by interviewer. The set of questions here ensures that you offer a perfect answer posed to you. So get preparation for your new job hunting
36 Payables Management Questions and Answers:
Table of Contents: Bar charts are suitables for:
A. minor works
B. major works
C. large projects
D. all the Above Works costing less than Rs. 20,000 and are treated as:
A. projects
B. major projects
C. minor projects
D. all the above Estimated time required to perform an activity, is known as:
A. event
B. dummy
C. duration
D. float If total float and duration of an activity are 5 and 10 days respectively, the particular activity can be:
A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above Which one of following represents an activity:
A. excavation for foundation
B. curing of concrete
C. setting of question paper
D. preparation of breakfast
E. all the above Pick up correct statement from the following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. CPM does not make any allowance for the uncertainties in the duration of time
D. In CPM, the time is related to cost
E. All the above The Modular co-ordination of construction means proper:
A. planning
B. designing
C. execution
D. all the above CPM family includes:
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. CPS (Critical Path Scheduling)
E. All the above Time which results in the leasi, possible construction cost of an activity, is known:
A. normal time
B. slow time
C. crash time
D. standard time Artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as:
A. event
B. free float
C. dummy
D. constant Overall in-charge of an organisation at the site responsible for the execution of the works, is:
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Program Evaluation and Review Technique (PERT) Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as:
A. duration
B. total flat
C. free float
D. interfering float Executive Engineer may have powers upto:
A. Rs. 25,000
B. Rs. 50,000
C. Rs. 100,000
D. Rs. 200,000
E. Rs. 500,000 The Critical path method:
A. is an improvement upon bar chart method
B. provides a realistic approach to daily problems
C. avoids delays which are very common in bar charts
D. was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
E. All the above The Critical Path Net Work helps an engineer:
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all the above Critical path lies along activities having total float:
A. positive
B. negative
C. zero
D. same Main principle of an organisation, is:
A. unity of command
B. cohegency
C. effective control at all levels
D. delegation of authority
E. all the above The site order book is used for recording:
A. instructions by the executive engineers
B. construction measurements
C. issue of store equipment's
D. names of the casual labour Salient feature of functional organisation is:
A. strict adherence to specifications
B. separation of planning and design part
C. each individual maintains functional efficiency
D. work is properly planned and distributed
E. all the above Difference between the time avail-to do a job and the time required to do the job, is known as:
A. event
B. float
C. duration
D. constraint Object of technical planning, is:
A. preparation of specifications
B. preparation of estimates
C. initiating the procurement action of resources
D. taking remedial action for likely bottleneck in the execution
E. all the above Various activities of project, are shown on bar charts by:
A. vertical lines
B. horizontal lines
C. dots
D. crosses. Most popular type of organisation used for Civil Engineering Constructions, is:
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation Pick up incorrect statement from the following:
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
E. None of these Top Payables Management Job Interview Questions and Answers A. instructions by the executive engineers
C. The activity which consumes maximum time, is called a node
36 Payables Management Interview Questions and Answers