Pick up incorrect statement from the following:
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
E. None of these

Payables Management Interview Question
Payables Management Interview Question

Answer:

C. The activity which consumes maximum time, is called a node

Download Payables Management Interview Questions And Answers PDF

Previous QuestionNext Question
The Time and progress chart of a construction, is also known as:
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. Critical path method chart
E. All the above
Most popular type of organisation used for Civil Engineering Constructions, is:
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation