First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Program Evaluation and Review Technique (PERT)

Payables Management Interview Question
Payables Management Interview Question

Answer:

A. Bar chart method


Previous QuestionNext Question
Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as:
A. duration
B. total flat
C. free float
D. interfering float
Overall in-charge of an organisation at the site responsible for the execution of the works, is:
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer