Payables Management Question: Download Questions PDF
Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as:
A. duration
B. total flat
C. free float
D. interfering float
![Payables Management Interview Answer Payables Management Interview Question](https://globalguideline.com/public/images/interview/1.png)
Answer:
C. free float