Payables Management Question:
Download Questions PDF

Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as:
A. duration
B. total flat
C. free float
D. interfering float

Payables Management Interview Question
Payables Management Interview Question

Answer:

C. free float

Download Payables Management Interview Questions And Answers PDF

Previous QuestionNext Question
Executive Engineer may have powers upto:
A. Rs. 25,000
B. Rs. 50,000
C. Rs. 100,000
D. Rs. 200,000
E. Rs. 500,000
First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Program Evaluation and Review Technique (PERT)