Cost Management Question: Download Questions PDF
The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?
A. Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs
Answer:
C. Determine Budget