Senior Project Officer Question:

How do you estimate in the three point estimating method?

Senior Project Officer Interview Question
Senior Project Officer Interview Question

Answer:

One optimistic estimate, a pessimistic estimate and one most likely estimate is considered for an activity. (Op estimate+6 X most likely+ pess. Estimate) is calculated and divided by 6. This result then may be further iterated. This is the estimate to be used."0"


Previous QuestionNext Question
What are processes and process groups?What are some techniques used for defining scope?