Electrical Engineering Question: Download Questions PDF
Prior to using an electric saw on a construction site, a user check finds that the insulation on the supply flex is damaged. The correct procedure would be to
Answer:
* a) Replace the cord with a new one
* b) Report the damage to a supervisor after use
* c) Repair the cord with insulation tape
* d) Report the damage to a supervisor before use
Answer – d
* b) Report the damage to a supervisor after use
* c) Repair the cord with insulation tape
* d) Report the damage to a supervisor before use
Answer – d
Download Electrical Engineering Interview Questions And Answers
PDF
Previous Question | Next Question |
Which of the following documents is non-statutory? | When carrying out repairs to the base of a street lighting column it is essential to wear |