Chemical Engineering Question:
Download Job Interview Questions and Answers PDF
Are there any general rules for flushing slurry lines?
Answer:
Slurry lines should be flushed with a minimum fluid velocity of 10 ft/s and the total flushing liquid volume should equal 3-6 times the total piping volume.
Download Chemical Engineering Interview Questions And Answers
PDF