How to schedule counter base maintenance plant for DG in power plant that need 800hr per month maint this steps i followed.
1)i have created meas pt with counter (IK01) created meas
document IK11 then schedule thru IP10.
but not getting due order list in ip24

SAP PM Interview Question
SAP PM Interview Question

Answer:

First of all, you cannot get 800 hrs per month...

For counter based... it will schedule in two days... like..
days and hours... but.. if u schedule in IP10..it wil take
the annual reading and schedule the dates.. So.. if the
running hrs didn't reach, but the date reached... so.. it
will open a order...

Give the annual reading according to the running hrs of the
DG.. then u will get