SAP PS Question:
Download Job Interview Questions and Answers PDF
How can PS be linked to COPA? How will the settlement take place in this case (when PS is linked to Controlling through COPA)?
Answer:
Settlement will take place via profitability segmenet .
Level 1 WBS should have settlement rule define to be
settled to PSG and level 2 WBS should be settled to
superior one WBS element .The main one level 1 WBS/ Project
will be settled to PSG , and variance will be posted to
COPA .
Level 1 WBS should have settlement rule define to be
settled to PSG and level 2 WBS should be settled to
superior one WBS element .The main one level 1 WBS/ Project
will be settled to PSG , and variance will be posted to
COPA .
Download SAP PS Interview Questions And Answers
PDF