Systems Support Manager (MIS) Question:
Download Questions PDF

Which of the following is(are) true of system analysts?

A. their responsibility is to analyze and design system software
B. they may be looked upon as an intermediary between users and programmers
C. they are heavily involved with the system-development life cycle
D. both (a) and (c)
E. None of the above

Systems Support Manager (MIS) Interview Question
Systems Support Manager (MIS) Interview Question

Answer:

D. both (a) and (c)

Download Systems Support Manager (MIS) Interview Questions And Answers PDF

Previous QuestionNext Question
An optional facilitates location program can be used to study

A. factory location alternative
B. warehouse location alternatives
C. plant location alternatives
D. All of the above
E. None of the above
Critical path of the PERT chart is:

A. path which takes the longest time to complete the project
B. the shortest path
C. both of the above
D. path which takes the shortest time to complete the project
E. None of the above