Capacitor Planning Question:

Download Job Interview Questions and Answers PDF

Measurement has revealed the following information on an operations system. Design capacity was 84 units per hour, planned losses were 12 units per hour, and actual output was 65 units per hour. What were the utilization and efficiency of the operation respectively?

Capacitor Planning Interview Question
Capacitor Planning Interview Question

Answer:

1. 77% & 90%
2. 78% & 90%
3. 54% & 92%
4. 68% & 83%
5. 77% & 84%

77% & 90%

Download Capacitor Planning Interview Questions And Answers PDF

Previous QuestionNext Question
Capacity is usually expressed in terms of?The following figures were reported at a management meeting for the kitchen facility of a restaurant - actual output was 62 hours, design capacity is 150 hours, and the effective capacity was 120 hours. What are respectively the kitchen facilitys utilization and efficiency?