PMI Certification Exam Question:
Download Questions PDF

Explain During project lose-out, the final task is to....
A. Verify that contractual obligations were met.
B. Transfer the deliverables to the client.
C. Reassign team member.
D. Complete performance/lessons-learned records.

Answer:

B. Transfer the deliverables to the client.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Explain The MOST effective method in developing a project team within a matrix organization is to follow
the:
A. communications plan.
B. Scope change control plan.
C. Staffing management plan.
D. Training development plan.
Explain The authority to accept or reject a requested change in a large and complex project, should rest
with _____?
A. The sponsor.
B. The president.
C. The change control board.
D. The client.