PMI Certification Exam Question: Download Questions PDF
Explain The authority to accept or reject a requested change in a large and complex project, should rest
with _____?
A. The sponsor.
B. The president.
C. The change control board.
D. The client.
E. The project manager.
Answer:
C. The change control board.