PMI Certification Exam Question:

Download Job Interview Questions and Answers PDF

Explain The MOST effective method in developing a project team within a matrix organization is to follow
the:
A. communications plan.
B. Scope change control plan.
C. Staffing management plan.
D. Training development plan.

PMI Certification Interview Question
PMI Certification Interview Question

Answer:

C. Staffing management plan.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Which of the following concepts are associated with the Cost of Quality in project management?
(Choose all that apply)
A. Appraisal costs
B. Management costs
C. Prevention costs
D. Failure costs
E. Planning costs
Explain During project lose-out, the final task is to....
A. Verify that contractual obligations were met.
B. Transfer the deliverables to the client.
C. Reassign team member.
D. Complete performance/lessons-learned records.