Payables Management Question: Download Payables Management PDF
The Critical Path Net Work helps an engineer:
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all the above
Answer:
D. all the above