PMI Certification Exam Question:
Download Questions PDF

Suppose A projects scope statements is developed during scope:
A. The initiation phase.
B. The implementation phase.
C. The planning phase.
D. The verification phase.
E. The definition phase.

Answer:

C. The planning phase.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Explain The determination of conformance with scope requirements is called ____?
A. Quality Planning.
B. Quality Control.
C. Quality Management.
D. Quality Assurance.
Explain Which of the following will have the greatest impact on a product or service?s reliability and
maintenance characteristics?
A. Function.
B. Implementation
C. Design.
D. Cost.
E. Fabrication.