PMI Certification Exam Question:

Explain The determination of conformance with scope requirements is called ____?
A. Quality Planning.
B. Quality Control.
C. Quality Management.
D. Quality Assurance.

PMI Certification Interview Question
PMI Certification Interview Question

Answer:

B. Quality Control.