PMI Certification Exam Question:
Download Questions PDF

Explain The determination of conformance with scope requirements is called ____?
A. Quality Planning.
B. Quality Control.
C. Quality Management.
D. Quality Assurance.

PMI Certification Interview Question
PMI Certification Interview Question

Answer:

B. Quality Control.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Work packages are described in the:
A. Work charter.
B. Work schedule.
C. Work breakdown structure.
D. Work project plan.
E. Statement of work.
Suppose A projects scope statements is developed during scope:
A. The initiation phase.
B. The implementation phase.
C. The planning phase.
D. The verification phase.
E. The definition phase.