PMI Certification Exam Question: Download Questions PDF
Explain Which of the following is NOT a function of a kick-off meeting?
A. Project cost estimation and presentation.
B. Introducing the stakeholders.
C. Identifying goals of the project.
D. Obtaining commitment from all participants.
![PMI Certification Interview Answer PMI Certification Interview Question](https://globalguideline.com/public/images/interview/31.png)
Answer:
A. Project cost estimation and presentation.