PMI Certification Exam Question:
Explain Although they have a variety of side-effects, the primary objective of incentive clauses in a
contract is to:
A. Aligning contractor and buyer goals.
B. Reduce risk for the contractor
C. Controlling contractor costs
D. Reduce costs to the buyer
E. Reducing production costs.

Answer:
A. Aligning contractor and buyer goals.