Manager Construction Question:
First method invented for planning projects, was:
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)
Tweet
Share
WhatsApp
Answer:
A. Bar chart method
Read All 45 Construction Manager Questions
Previous Question
Next Question
During night work who does CM contact?
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to:
A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above