PMI Certification Exam Question: Download PMI Certification PDF
Which of the following concepts are associated with the Cost of Quality in project management?
(Choose all that apply)
A. Appraisal costs
B. Management costs
C. Prevention costs
D. Failure costs
E. Planning costs
Answer:
A. Appraisal costs
C. Prevention costs
D. Failure costs
C. Prevention costs
D. Failure costs