Chemical Engineering Question: Download Chemical Engineering PDF

What factors should be compared when evaluating cooling tower bids?

Tweet Share WhatsApp

Answer:

Examining the following factors should allow for a reasonable evaluation of cooling towers:

1) Purchased cost

2) Installed cost

3) Fan energy consumption

4) Pump energy consumption

5) Water use

6) Water treatment costs

7) Expected maintenance costs

8) Worker safety requirements

9) Environmental safety

10) Expected service life

Download Chemical Engineering PDF Read All 151 Chemical Engineering Questions
Previous QuestionNext Question
For a heat exchanger, will the overall heat transfer coefficient increase along with an increase in LMTD (log mean temperature difference) around the unit?What could be a possible cause for sudden foaming in a cooling tower?