Suppose A primary function of the change control board is to:
A. Review the impact of change request.
B. Issue change requests.
C. Represent top management interests.
D. Identify new areas of project work.
E. Assign new team members to increase output.

PMI Certification Interview Question
PMI Certification Interview Question

Answer:

A. Review the impact of change request.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Explain The PERT method is MOST used in situations where:
A. It is important to know the interrelationships of activities.
B. Little is known about the cost estimated related to the project.
C. Little experience exists on which to base estimated of activity duration.
D. Resource requirements are well defined.
Tell me which of the following terms is used to refer to the adjustment of task schedules to result in more
effective human resource deployment?
A. Resource fast tracking.
B. Resource planning
C. Resource leveling.
D. Resource crashing.
E. Resource loading.