Chemical Engineering Question: Download Chemical Engineering PDF

IS there a rule of thumb to estimate the footprint of a cooling tower during design phase?

Tweet Share WhatsApp

Answer:

Over the years, this one has seemed to stand the test of time:

Every million Btu/h of tower capacity will require approximately 1000 ft2 of cooling tower basin area.

Download Chemical Engineering PDF Read All 151 Chemical Engineering Questions
Previous QuestionNext Question
What could be a possible cause for sudden foaming in a cooling tower?When specifying a cooling tower, should I look up historic wet bulb temperatures for my area or should I take measurements?