Explain During execution, a resource is added to the project team. What effect will this have on the
project?
A. The effect cannot be determined.
B. The project duration will be shortened.
C. A scope change will be required
D. The quality of the project will be increased.

PMI Certification Interview Question
PMI Certification Interview Question

Answer:

A. The effect cannot be determined.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
An individuals willingness to take a risk can be determined by:
A. Decision tree modeling.
B. Monte Carlo method,
C. Sensitivity analysis.
D. Utility theory.
E. Maslows hierarchy of needs.
One a project, quality should generally be of:
A. Equal priority with schedule, but higher priority than cost.
B. Higher priority than cost and schedule.
C. Equal priority with cost, but higher priority than schedule.