PMI Certification Exam Question: Download Questions PDF
Explain During execution, a resource is added to the project team. What effect will this have on the
project?
A. The effect cannot be determined.
B. The project duration will be shortened.
C. A scope change will be required
D. The quality of the project will be increased.
![PMI Certification Interview Answer PMI Certification Interview Question](https://globalguideline.com/public/images/interview/31.png)
Answer:
A. The effect cannot be determined.