PMI Certification Exam Question:
Download Questions PDF

Explain Conflict resolution techniques that may be used on a project include:
A. Withdrawing, compromising, controlling, and forcing.
B. Controlling forcing smoothing, and withdrawing.
C. Confronting, compromising, smoothing and directing.
D. Smoothing, confronting, forcing, and withdrawing.

PMI Certification Interview Question
PMI Certification Interview Question

Answer:

D. Smoothing, confronting, forcing, and withdrawing.

Download PMI Certification Interview Questions And Answers PDF

Previous QuestionNext Question
Explain Payback period analysis identifies that point in time when:
A. Profit maximum is realized.
B. Unit profit is realized.
C. Monthly revenue exceeds monthly costs.
D. Cumulative revenue exceeds cumulative costs.
Ho to determine the staffing requirements of the project, the project mange FIRST needs a(n);
A. Resource breakdown schedule.
B. Responsibility assignment matrix.
C. Work breakdown structure.
D. Organization chart.