Can we have get report of only night/3rd shifts of entire month? what is t-code?

Tweet Share WhatsApp

Answers:

Answer #1pl share your answer

Answer #2By using tcode coois in that select confirmations execute the report and then filter with shift

Answer #3Yes.. with the help of T-code SHR3


Answer #4Report processing in Background. SM37 Tcode

Answer #5SHR1

Download SAP PP PDF Read All 21 SAP PP Questions
Previous QuestionNext Question
Can we create Production order without bom and routing?During data transfer from source file to sap, if there are documents or drawings attached to each material in data, what will happen to such documents or drawings? can all documents/drawings be transfer to sap at once or we have to do it seperately?