What is the use of item number in maintenance order?
Answer:
Item number refers to the number (not material number) to
identify the material component that is to be used for an
operation in the maintenance order.It is generally given in
increments of 0010.It is the first field in the Components
tab of a maintenance order.
identify the material component that is to be used for an
operation in the maintenance order.It is generally given in
increments of 0010.It is the first field in the Components
tab of a maintenance order.