The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as:
A. event
B. free float
C. dummy
D. constant

Management Interview Question
Management Interview Question

Answer:

C. dummy

Download Management Interview Questions And Answers PDF

Previous QuestionNext Question
The overall in-charge of an organisation at the site responsible for the execution of the works, is:
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer
The time which results in the leasi, possible construction cost of an activity, is known:
A. normal time
B. slow time
C. crash time
D. standard time