Tell me why are pull-out tests performed for soil nails?

Answer:

Pull out tests are performed for primarily the following reasons:
☛ In order to detect and the verification of the bond strength among the soil and the grout adopted during the design of soil nails. This is considered to be as the primary objective of performing pull out tests for soil nails.
☛ For the detection of any slippage or occurrence of creeps.
☛ To detect the elastic and deformations (plastic) of any of the test nails employed. Observations are made during the loading and unloading cycles of the soil nails repetitively.
☛ To achieve the perfect balance the test nails should always be loaded so that the ultimate soil/grout mixture with an upper limit of 80%.