Project Coordinator Question:
How do you estimate the cost of projects?
Answer:
1. Create the WBS of the project.
2. Assign TeamMember for each Task
3. Prepare the schedule of the Project.
4. Calculate the Effort based on the schedule & Number of
Team members
For example:
Project Shedule is 2 Month with 2 Team Member( Considering
8 Hrs per day)
That Means Effort is 4 Manmonths
Assume that Per Hour cost is 20$
One day cost per resource is 8 * 20 = 160$
One day Cost for two resources are 165*2 = 320$
Number of Working days in one Month is 22 days.
Number of Working days in 2 Months are 2* 22 = 44 days.
Add 4 Hours of Project Management that means Number of
days for project Management is 22 Days.
Total Number of days = 44+22 = 66 days
The Total Poroject Cost = 66 *320$ = 21120$
( Note: I have Assumed cost per hour is 20$ for Project Management Also. This cost may be diferent
I have Considered this Project executed @ offOsore
Onsite Cost will be more.
If the project is executed in ofshore/Onsite model , cost
will be diferent))
2. Assign TeamMember for each Task
3. Prepare the schedule of the Project.
4. Calculate the Effort based on the schedule & Number of
Team members
For example:
Project Shedule is 2 Month with 2 Team Member( Considering
8 Hrs per day)
That Means Effort is 4 Manmonths
Assume that Per Hour cost is 20$
One day cost per resource is 8 * 20 = 160$
One day Cost for two resources are 165*2 = 320$
Number of Working days in one Month is 22 days.
Number of Working days in 2 Months are 2* 22 = 44 days.
Add 4 Hours of Project Management that means Number of
days for project Management is 22 Days.
Total Number of days = 44+22 = 66 days
The Total Poroject Cost = 66 *320$ = 21120$
( Note: I have Assumed cost per hour is 20$ for Project Management Also. This cost may be diferent
I have Considered this Project executed @ offOsore
Onsite Cost will be more.
If the project is executed in ofshore/Onsite model , cost
will be diferent))
Previous Question | Next Question |
How do you speedup the project delivery without affecting the cost? | What is basics of Agile/Scrum development? |