LoadRunner Question:
How did you plan the Load? What are the Criteria?
Answer:
Load test is planned to decide the number of users, what kind of machines we are going to use and from where they are run. It is based on 2 important documents, Task Distribution Diagram and Transaction profile. Task Distribution Diagram gives us the information on number of users for a particular transaction and the time of the load. The peak usage and off-usage are decided from this Diagram. Transaction profile gives us the information about the transactions name and their priority levels with regard to the scenario we are deciding.
Previous Question | Next Question |
What does vuser_end action contain? | How did you find database related issues? |