Agile Testing Question:

Explain what is the difference between burn-up and burn-down chart?

Tweet Share WhatsApp

Answer:

Burn-up and burn-down charts are used to keep track the progress of the project.

Burn-up charts represent how much work has been completed in any project whereas Burn-down chart represents the remaining work in a project.

Download Agile Testing PDF Read All 85 Agile Testing Questions
Previous QuestionNext Question
What is Application Binary Interface?Explain me what is difference between Epic, User stories & Tasks?