Agile Testing Question:
Download Job Interview Questions and Answers PDF
Explain what is the difference between burn-up and burn-down chart?
Answer:
Burn-up and burn-down charts are used to keep track the progress of the project.
Burn-up charts represent how much work has been completed in any project whereas Burn-down chart represents the remaining work in a project.
Burn-up charts represent how much work has been completed in any project whereas Burn-down chart represents the remaining work in a project.
Download Agile Testing Interview Questions And Answers
PDF
Previous Question | Next Question |
What is Application Binary Interface? | Explain me what is difference between Epic, User stories & Tasks? |