Explain what is the difference between burn-up and burn-down chart?

Agile Testing Interview Question
Agile Testing Interview Question

Answer:

Burn-up and burn-down charts are used to keep track the progress of the project.

Burn-up charts represent how much work has been completed in any project whereas Burn-down chart represents the remaining work in a project.