MSF (Microsoft Solution Framework) Question:
Explain Trade-off triangle?
Answer:
It is suggested that a project is a balance between following variables:
a. Resources
b. Schedule
c. Features
These variables are represented with the sides of the trade-off triangle. The trade-off triangle suggests that if any of the side changes in the triangle, then other sides (one or both) need to change in order to maintain balance.
a. Resources
b. Schedule
c. Features
These variables are represented with the sides of the trade-off triangle. The trade-off triangle suggests that if any of the side changes in the triangle, then other sides (one or both) need to change in order to maintain balance.