Certified Quality Engineer Question:
Described about bug life cycle?
Answer:
★ When a tester finds a bug .The bug is assigned with NEW or OPEN status.
★ The bug is assigned to development project manager who will analyze the bug .He will check whether it is a valid defect. If it is not valid bug is rejected, now status is REJECTED.
★ If not, next the defect is checked whether it is in scope. When bug is not part of the current release .Such defects are POSTPONED
★ Now, Tester checks whether similar defect was raised earlier. If yes defect is assigned a status DUPLICATE
★ When bug is assigned to developer. During this stage bug is assigned a status IN-PROGRESS
★ Once code is fixed. Defect is assigned with FIXED status.
★ Next the tester will re-test the code. In case the test case passes the defect is CLOSED
★ If the test case fails again the bug is RE-OPENED and assigned to the developer. That's all to Bug Life Cycle.
★ The bug is assigned to development project manager who will analyze the bug .He will check whether it is a valid defect. If it is not valid bug is rejected, now status is REJECTED.
★ If not, next the defect is checked whether it is in scope. When bug is not part of the current release .Such defects are POSTPONED
★ Now, Tester checks whether similar defect was raised earlier. If yes defect is assigned a status DUPLICATE
★ When bug is assigned to developer. During this stage bug is assigned a status IN-PROGRESS
★ Once code is fixed. Defect is assigned with FIXED status.
★ Next the tester will re-test the code. In case the test case passes the defect is CLOSED
★ If the test case fails again the bug is RE-OPENED and assigned to the developer. That's all to Bug Life Cycle.