Payables Management Question:
Download Questions PDF

Bar charts are suitables for:
A. minor works
B. major works
C. large projects
D. all the Above

Payables Management Interview Question
Payables Management Interview Question

Answer:

A. minor works

Download Payables Management Interview Questions And Answers PDF

Previous QuestionNext Question
The Final technical authority of a project lies with:
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Works costing less than Rs. 20,000 and are treated as:
A. projects
B. major projects
C. minor projects
D. all the above