Chemical Engineering Question:

Are there any general rules for flushing slurry lines?

Tweet Share WhatsApp

Answer:

Slurry lines should be flushed with a minimum fluid velocity of 10 ft/s and the total flushing liquid volume should equal 3-6 times the total piping volume.