Chemical Engineering Question: Download Chemical Engineering PDF

Are there any general rules for flushing slurry lines?

Tweet Share WhatsApp

Answer:

Slurry lines should be flushed with a minimum fluid velocity of 10 ft/s and the total flushing liquid volume should equal 3-6 times the total piping volume.

Download Chemical Engineering PDF Read All 151 Chemical Engineering Questions
Previous QuestionNext Question
What is a good way to get started in doing a plant-wide steam consumption analysis?How can you determine the proper pipe thickness for a slurry line?